SHREVEPORT-BOSSIER CITY — The new Jimmie Davis Bridge now spans the Red River on its girders, but drivers are still using the old crossing. The distinction matters as construction enters a more visible phase: the state now expects the new four-lane bridge to open in mid to late 2027, a later target than the one announced when construction began.

The Louisiana Department of Transportation and Development's current project page lists a May 2024 start, a $361.7 million cost and James Construction Group as contractor. It says the new bridge should open to traffic in mid to late 2027. It separately says the entire project, including the conversion of the existing bridge into a pedestrian and bicycle linear park, is expected to finish in late 2028. The page's brief project-details box says 'End of 2027' for a finish date, so even the agency's own page uses more than one milestone. None should be mistaken for a guaranteed opening day.

How the schedule changed

In its April 2024 construction kickoff announcement, DOTD projected that the new bridge would be complete in late 2026. By August 2026, the agency said the girders had been installed across the river and described mid-2027 as the overall project's anticipated completion, subject to weather and other factors. Its more detailed project page now separates opening the vehicle bridge from finishing the linear park, placing the latter in late 2028. The public notices establish a changed projection; they do not, on their own, identify a cause for the difference.

The August notice also dates the existing bridge to 1968. The state's plan is to keep that structure and remake it as a river crossing for people walking and cycling, linked to existing trails on both banks. The new road bridge is being built just north of it. Approaches on both sides are being widened and rebuilt for two lanes in each direction, a raised median and new turn openings, according to the project description. That is more work than simply placing a new span over the river.

The latest construction milestone

DOTD said in August that girder installation had connected the new structure across the river. A September 30 traffic notice then scheduled a concrete deck pour for the night of October 9 and early October 10, with temporary Clyde Fant Parkway closures. The deck is the road surface. We found the scheduling notice, not a subsequent agency confirmation that the pour was completed on those dates, and are treating it as a planned operation rather than a finished milestone.

The same notice says work continues on the LA 511 approaches and advises caution around intermittent lane closures. Drivers who need a current route should check Louisiana 511 before traveling; a past closure notice is not a live traffic update.

What remains to be answered

The published project records give the public a useful timeline, but they leave two practical questions. What changed the opening projection between the 2024 kickoff and the current project page? And which pieces of work must be finished before cars can use the new span, as opposed to the later park work? We have not found a DOTD explanation that assigns the schedule change to a particular delay, design decision or cost increase. The current $361.7 million figure is the agency's project cost, not a documented measure of any overrun.

For now, the clearest reading of the state's records is three dates, not one: construction started in May 2024; the new vehicle bridge is projected to open in mid to late 2027; and the full project, including the linear park, is projected to wrap up in late 2028. Those projections may change. DOTD's project page and traffic bulletins are the records to consult for the next confirmed milestone.